| | General Building Plans | Target Dates for Beginning and Completion |
| Initial Step | Submitted all legal documents to obtain approval of the orphanage name and incorporating in Mexico and the United States as The City of Children of Matamoros A.C. | 2003 - 2004 |
| Step # 1 | Finalized transaction of 17 Acres of Donated Land with all legal requirements | 2003 |
| Step # 2 | Conducted a Study to Determine the Need and Made Application for the Department for the Integration of Families (DIF) Approval in Mexico | 2003-2004 |
| Step # 3 | Developed Architectural Drawings of Orphanage and Obtained Building Permit | 2003-2005 |
| Step # 4 | Prepared the Grounds for Construction Work | 2004 ongoing |
| Step # 5 | Prepared Grounds for Construction and Foundation for Eight (8) Buildings | Beginning 2005 – January 2007 |
| Step # 6 | Purchased Material for Building Assembly | Beginning 2005 – January 2007 |
| Step # 7 | Proceed with Foundation and Block Work for All Buildings | August 2005 – April 2006 |
| Step # 8 | Begin and Complete the Roof Work for 8 Buildings | September 2005 – May 2006 |
| Step # 9 | Completely Finish All Buildings | September 2005 – January 2007 |
| Step # 10 | Equip All Buildings and Grounds | September 2005 – January 2007 |